1. Wastewater Treatment Procedures by Campus

1. The wastewater treatment procedures on NCUE’s Jinde and Shida Campuses are as follows:

(1) Jinde Campus:

In accordance with the Waste Disposal Act, NCUE commissions qualified contractors to remove and treat laboratory liquid waste as industrial waste. With the approval of the Environmental Protection Bureau of Changhua County Government, NCUE cancelled the water pollution control permit for Jinde Campus, which is no longer subject to regulatory control. The original wastewater treatment facilities remain in normal operation.

(2) Shida Campus: The wastewater treatment plant mainly treats domestic wastewater.

2. Wastewater Collection, Monitoring, and Compliance

2. All wastewater on NCUE’s campuses is collected through sewer pipes and treated at the campus wastewater treatment plants. It is then discharged through the outlets that NCUE has registered with the regulatory authority. In accordance with the Water Pollution Control Act (Figure 1) (https://law.moj.gov.tw/ENG/LawClass/LawAll.aspx?pcode=O0040001) and the Water Pollution Control Act Enforcement Rules (Figure 2) (https://law.moj.gov.tw/ENG/LawClass/LawAll.aspx?pcode=O0040002), NCUE files the water quality test results for raw wastewater and effluent from its wastewater treatment plants twice a year: every July for January–June of that year, and every January for July–December of the previous year.

Figure 1. The Web Page on the Laws & Regulations Database of the Republic of China – Water Pollution Control Act
Figure 1. The Web Page on the Laws & Regulations Database of the Republic of China – Water Pollution Control Act
Figure 2. The Web Page on the Laws & Regulations Database of the Republic of China – Water Pollution Control Act Enforcement Rules
Figure 2. The Web Page on the Laws & Regulations Database of the Republic of China – Water Pollution Control Act Enforcement Rules

(1) Figure 3 is a screenshot of NCUE’s reporting page on the Ministry of Environment’s “Wastewater Management System for Industrial and Sewerage Systems” (WPMIS).

Figure 3. Screenshot of the "Wastewater Management System for Industrial and Sewerage Systems" reporting page of the Ministry of Environment
Figure 3. Screenshot of the "Wastewater Management System for Industrial and Sewerage Systems" reporting page of the Ministry of Environment

(2) Reporting Website: Environmental Management System of Taiwan’s Ministry of Environment: https://ems.moenv.gov.tw/

(3) Figures 4-9 show photos of the sewage treatment plants.

Figure 4. Sewage Treatment Plant on Jinde Campus
Figure 4. Sewage Treatment Plant on Jinde Campus
Figure 5. Sewage Treatment Plant on Jinde Campus
Figure 5. Sewage Treatment Plant on Jinde Campus
Figure 6. Sewage Treatment Plant on Jinde Campus
Figure 6. Sewage Treatment Plant on Jinde Campus
Figure 7. Sewage Treatment Plant on Jinde Campus
Figure 7. Sewage Treatment Plant on Jinde Campus
Figure 8. Sewage Treatment Plant on Shida Campus
Figure 8. Sewage Treatment Plant on Shida Campus
Figure 9. Sewage Treatment Plant on Shida Campus
Figure 9. Sewage Treatment Plant on Shida Campus

(4) In accordance with the Water Pollution Control Act, NCUE calibrates the effluent water meters of its sewage treatment plants once a year. Figures 10–11 show the effluent water meter calibration report issued by a testing institution accredited by the Ministry of Environment.

Figure 10. Water meter calibration report for NCUE's sewage treatment plants (Page 1)
Figure 10. Water meter calibration report for NCUE's sewage treatment plants (Page 1)
Figure 11. Water meter calibration report for NCUE's sewage treatment plants (Page 2)
Figure 11. Water meter calibration report for NCUE's sewage treatment plants (Page 2)

(5) In accordance with the Water Pollution Control Act, water quality testing is conducted every six months (as shown in Figures 12-15).

Figure 12. Effluent water quality testing at the sewage treatment plant on Jinde Campus
Figure 12. Effluent water quality testing at the sewage treatment plant on Jinde Campus
Figure 13. Effluent water quality testing at the sewage treatment plant on Jinde Campus
Figure 13. Effluent water quality testing at the sewage treatment plant on Jinde Campus
Figure 14. Effluent water quality testing at the sewage treatment plant on Shida Campus
Figure 14. Effluent water quality testing at the sewage treatment plant on Shida Campus
Figure 15. Effluent water quality testing at the sewage treatment plant on Shida Campus
Figure 15. Effluent water quality testing at the sewage treatment plant on Shida Campus

(6) In accordance with the Water Pollution Control Act and Waste Disposal Act, sludge removal and treatment operations are conducted once every 2 years (as shown in Figures 16-19)

Figure 16. Sludge removal at the sewage treatment plant on Jinde Campus
Figure 16. Sludge removal at the sewage treatment plant on Jinde Campus
Figure 17. Sludge removal at the sewage treatment plant on Jinde Campus
Figure 17. Sludge removal at the sewage treatment plant on Jinde Campus
Figure 18. Sludge removal at the sewage treatment plant on Jinde Campus
Figure 18. Sludge removal at the sewage treatment plant on Jinde Campus
Figure 19. Sludge removal at the sewage treatment plant on Shida Campus
Figure 19. Sludge removal at the sewage treatment plant on Shida Campus

3. In 2025, the treatment performance, periodic inspection and reporting records, and all operations of the sewage treatment plants on both campuses passed official reviews and tests, and the plants operated normally.