NCUE_Logo  National Changhua University of Education Sustainable Development Goals, SDGs 

SDG7.2.2 Upgrade buildings to higher energy efficiency

1. NCUE holds an annual energy-saving and carbon-reduction meeting to evaluate plans for the replacement of existing equipment with energy-saving equivalents the following year. At least NT$5 million is invested annually to replace energy-consuming equipment, which is forecasted to achieve the goal of increasing total energy efficiency by at least 1% per year (the goal is to save 150,000 kWh or more annually).

1.1 NCUE has implemented a range of major energy conservation and carbon reduction measures from 2019 to 2022.
7.2.2
1.2 In response to the national policy of promoting renewable energy, NCUE installed solar power cells on the roof of the Jinde campus gymnasium in 2017. The capacity of the generator is 467.28 kWp and it is expected to generate 625,945 kWh of power annually. The event was highlighted in the regional Changhua news (for details of the news report, please refer to http://epage.ncue.edu.tw/files/14-1000-13227,r9-1.php
7.2.2
The above picture shows the gymnasium’s roof with installed solar cells.

2. In response to the national policy, NCUE plans to complete the second installation of photovoltaic solar cells on the roofs of other school buildings by the end of 2022. The total capacity of the solar power system on the Jinde campus is expected to be 2,085.75 Kw, and that on the Baoshan campus is expected to be 571.5 kW. In addition to reducing the net energy load of the buildings, in certain scenarios (such as off-peak months), the buildings’ energy needs can be entirely met by the solar power system. By reducing the amount of energy drawn from the main grid, local line loss can be reduced by approximately 3%, improving energy efficiency. Moreover, solar panels block direct sunlight that would otherwise be absorbed by the roof. According to research, direct sunlight on the roof can be reduced by 38% with the use of solar panels and roof temperature, consequently, can be reduced by 2.8 °C. Thus, the temperature inside the buildings can be lowered, use of air conditioners can be reduced, and energy efficiency can be improved.
3. The (partial) design and layout of the rooftop photovoltaic solar cells on each building in the Jinde and Baoshan campuses from 2021 to 2022 are as follows:

Solar Power System Installation Plan for the Jinde and Baoshan Campuses in 2021-2022

Campus

Building

Estimated capacity (kWp)

(Total)

Estimated power generation (kwh/year)

(Total)

Jinde Campus

Qiaosi Building

75.75

2,085.75

kWp

94,687

2,607,183kWh

Baisha Building

191.625

239,531

Zhishan Building

48

60,000

Mingde Building

64.125

80,156

Educational Building

92.25

115,312

No. 8 Dormitory

189

236,250

No. 7 Dormitory

181.5

226,875

No. 6 Dormitory

88.5

110,625

Hubin Building

123

153,750

Library

146.625

183,281

Comprehensive Center

103.875

129,843

Student Canteen

146.625

183,281

Shengyang Building

99.375

124,218

Xuesi Building

36

45,000

Wang Jinping Activity Center

153.75

192,187

Wang Jinping Swimming Pool

242.25

302,812

Old Activity Center

103.5

129,375

Baoshan Campus

No. 9 Dormitory

99.75

571.25 kWp

125,625

714,375

kWh

First Educational Building

69.75

126,563

Engineering College Building

139.5

174,375

Jingshi Building

114.375

142,969

Lixing Building

148.125

185,156

4.    For the complete layout of the solar power system on the roofs of each building, please refer to Annex 7.2.2A: Layout of Photovoltaic Solar Devices on the Roofs of the Buildings in the Jinde and Baoshan campuses.
5.    NCUE is planning the installation of new rooftop and ground-based solar photovoltaic devices in 2023. It is estimated that between 2023 and 2024, an additional 510.04 kWp and 473.14 kWp of capacity will be added to the Jinde and Baoshan campuses, respectively (see the table below).

Campus

New Location

Estimated Capacity (kWp)

(Total)

Estimated Power Generation (kWh/year)

(Total)

Jinde Campus

No. 3 Dormitory

259.94

510 .04kWp

324,925

637,550 kWh

No. 5 Dormitory

69.7

87,125

Parking lot at the East Gate

102.5

128,125

Left and right sides of the Torch Tower

77.9

97,375

                 

Baoshan Campus

Behind No. 9 Dormitory

138.99

473.14

kWp

173,737

591,424

kWh

Parking lot of the No. 9 Dormitory next to the Baoshan Road

123.41

154,262

Parking lot of the First Educational Building next to the Baoshan Road

113.98

142,475

Parking lot of the Second Educational Building

96.76

120,950


The schedule of the solar power plant project is as follows:

Campus

Year

Newly Added Capacity (kWp)

Accumulated Capacity (kWp)

Estimated Annual Power Generation (kWh)

Jinde Campus

Before 2020

467

467

583,750

2021~2022

2085.75

2552.75

3,190,933

2023~2024

510.04

3062.79

3,828,483

Baoshan Campus

Before 2020

0

0

0

2021-2022

571.5

571.5

714,375

2023-2024

473.14

1044.64

1,305,799

6. The complete design and layout of the 2023-2024 solar energy project can be found in the Annex 7.2.2B: 2023-2024 Solar Energy Project of NCUE Jinde Campus and Baoshan Campus.
 